Search by
Factual background and parties
Groupe Piché Construction (2005) inc. (Groupe Piché) acted as a subcontractor to 9356-0175 Québec inc. (CIBS) on a construction project launched by the City of Montréal. The project involved transforming an existing building into a cultural and community centre pursuant to a public call for tenders issued by the City. CIBS held the main contract with the City, and Groupe Piché was engaged under a subcontract to perform part of the work.
In its originating application, Groupe Piché sued CIBS for a total of $430,935.69. This amount included, among other components, a specific claim described as a “Demande de compensation” of $185,394.76. That compensation claim corresponded to a 180-working-day extension to the construction schedule, allegedly attributable to delays that arose during the execution of the work. According to Groupe Piché, the delays caused it additional costs for which it sought reimbursement from CIBS.
CIBS, in turn, implicated its surety or guarantor, Compagnie d’Assurance Trisura Garantie (Trisura), as a defendant in warranty. CIBS also sought to shift part or all of the alleged responsibility to the City of Montréal by way of an Acte d’intervention forcée (forced intervention / appel en garantie), contending that the City’s conduct on the project lay at the root of the complained-of delays.
Nature of the compensation and alleged delays
The $185,394.76 claim for compensation was framed as damages payable to Groupe Piché for an extension of 180 working days to complete its subcontracted works. CIBS’s amended summary of defense asserted that this delay, and thus the associated compensation claimed by Groupe Piché, was not the result of its own fault, but rather of the City’s conduct in administering the project.
Specifically, CIBS alleged that the City had issued a multiplicity of change requests, often late, poorly timed, and processed too slowly. The accumulation of these changes, and the pace at which they were handled, was said to have caused cascading delays on the site. CIBS claimed that these delays generated the cost overruns for which Groupe Piché was now suing CIBS, meaning that the City should ultimately bear the responsibility if those amounts were found payable.
The pleadings tied this “Demande de compensation” to existing documentation. CIBS pointed to Groupe Piché’s own claim documents, an internal CIBS claim against the City, and CIBS’s account statement, in which the same compensation amount and its link to City-caused delays appeared. On that basis, CIBS maintained that the same claim for schedule extension and related costs was incorporated into its warranty claim against the City.
Procedural context and the City’s motion
The decision in question does not resolve the underlying construction dispute on the merits. It instead addresses a procedural “Demande” by the City of Montréal. The City asked the Superior Court to declare CIBS’s Acte d’intervention forcée inadmissible (irrecevable) under article 168(2) of the Code of Civil Procedure (C.p.c.) and to find that the forced intervention was abusive within the meaning of articles 51 and following C.p.c.
The City argued that the forced intervention did not fulfil the conditions of article 184(3) C.p.c., which governs forced interventions including appels en garantie. In its view, there were no sufficient factual allegations that could support a condemnation against the City, even if all facts pleaded were taken as true. It highlighted that Groupe Piché’s main action on account (action sur comptes) was solely directed at CIBS and contained no allegations against the City. The City further emphasized that it was not a party to the subcontract between Groupe Piché and CIBS and therefore should not be brought into a dispute arising out of that subcontract.
On the abuse front, the City pointed to prior unsuccessful joinder motions rejected by a special clerk, the lack of response by CIBS’s counsel to letters warning of the City’s intention to bring the inadmissibility motion, and the fact that the City had already been required to participate in an out-of-court examination. In the City’s submission, these elements showed that the forced intervention was not only legally baseless but also abusive in the procedural sense.
Legal framework on forced intervention and inadmissibility
The Court began by setting out the general rules governing forced intervention and exclusionary motions. Under article 184(2) C.p.c., there is forced intervention where a party brings in a third person so that the third party can intervene in the same proceeding, either to allow a complete resolution of the dispute or to have the judgment made opposable to that third party, including where a party asserts a warranty claim against the third party.
The appellate jurisprudence characterizes an appel en garantie as a specific form of forced intervention by which the main defendant seeks a condemnation against a third party that would indemnify it, in whole or in part, for any eventual judgment rendered against the defendant in the main action. For such a call in warranty to be proper, two connections are required: a legal link between the party calling in warranty and the party called in warranty (here, between CIBS and the City) and a sufficient connexity between the warranty claim and the main claim to avoid the risk of contradictory judgments if they were heard in separate proceedings.
Separately, article 168(2) C.p.c. permits a party to argue that a claim or defense is inadmissible when it is not founded in law even if the alleged facts are assumed to be true. The Court recalled a well-established line of authority stating that, on such an inadmissibility motion, the judge must: take as true the factual allegations and the supporting documents; distinguish between facts and legal qualification; refrain from weighing the likelihood of success of the case; and determine only whether the factual allegations and attached exhibits are capable of giving rise to the conclusions sought. A strong principle of prudence applies—if there is doubt, or if the issues are complex, the courts should generally refuse to strike a claim at the preliminary stage and should allow the matter to proceed to a full hearing on the merits.
Application of these standards to the City’s challenge
The City’s principal legal argument was that there was no sufficient legal link to justify an appel en garantie because there was no direct contract or extracontractual relationship between Groupe Piché and the City. The Court rejected this reading of the law. The relevant link for an appel en garantie is between the party calling in warranty (CIBS) and the party called in warranty (the City), not between the plaintiff in the main action (Groupe Piché) and the third party.
On the facts alleged, the Court found that there was at least a prima facie contractual relationship between CIBS and the City, since CIBS held the main contract for the City’s public project. That satisfied the requirement of a legal link between the warranty claimant and the party in warranty. Moreover, CIBS’s amended summary defense now expressly alleged that the delays underpinning Groupe Piché’s “Demande de compensation” were caused by the City’s negligence, omissions, and abuse of rights in managing changes and processing them.
The City argued that this allegation—particularly as framed in paragraph 11.2 of the amended summary defense—was speculative, unsupported by concrete facts, and effectively acknowledged by CIBS as hypothetical in other parts of the pleading. The City asserted that merely stating the City “could” be responsible for the delays, without detailed factual underpinnings and in light of the doctrine of relativity of contracts, could not suffice to ground a valid warranty action.
The Court nonetheless concluded that, once the relevant allegations and exhibits (including the referenced documents showing the compensation claim and its inclusion in CIBS’s claim against the City) were taken as true, the forced intervention cleared the relatively low threshold that applies at the stage of an inadmissibility motion. It was logically conceivable that a trial judge, after hearing full evidence on the cause of delays and the impact of the City’s change directives, could attribute part of the responsibility for the compensation claim to the City. Questions about the City’s detailed contractual obligations and the precise interpretation of the specifications (cahier des charges) were matters reserved for the trial judge, not for determination on a preliminary motion.
Connexity, risk of conflicting judgments and decision on abuse
The Court also found that there was sufficient connexity between Groupe Piché’s main claim against CIBS and CIBS’s warranty claim against the City. Both turned on the same central factual issue: whether the City’s behaviour (including numerous, late, and slowly processed change requests) was responsible for delays and additional costs claimed as the 180-day extension compensation. Because the same “Demande de compensation” formed part of both Groupe Piché’s claim against CIBS and CIBS’s claim against the City, the risk of contradictory findings on delay causation and its financial consequences was real if different courts were to hear the principal and warranty actions separately.
On the allegation of abuse, the Court held that the Acte d’intervention forcée was not manifestly abusive on its face, particularly in light of the newly amended summary of defense and the supporting documentation. While the City complained about earlier failed joinder motions and the procedural burden of examinations, those elements did not, at this point, justify a finding of abusive procedure against CIBS. The Court left open the possibility for the City to raise an abuse argument again after a full evidentiary record is developed at trial, should the warranty claim ultimately prove unfounded or frivolous in substance.
Outcome and costs
In conclusion, the Superior Court refused to strike down the forced intervention. It held that CIBS’s Acte d’intervention forcée against the City of Montréal, supported by the amended summary defense and exhibits, contained sufficiently detailed allegations capable of giving rise to the conclusions sought if proven. The Court emphasized that it was premature and imprudent to terminate the warranty claim at this stage, and that it was the role of the trial judge to assess the evidence on the City’s conduct, the project delays, and the resulting compensation claim.
The Court therefore dismissed the City of Montréal’s application for inadmissibility and abuse, with legal costs against the City. The successful parties in this interlocutory decision are CIBS (9356-0175 Québec inc.) and its surety, Compagnie d’Assurance Trisura Garantie. The judgment does not, however, adjudicate or quantify the substantive monetary claims between Groupe Piché, CIBS, and the City; it only orders that costs (“frais de justice”) be borne by the City. Because the decision does not specify any dollar amount for those costs, the exact total monetary award in favour of the successful parties cannot be determined from this judgment alone.
Download documents
Plaintiff
Defendant
Court
Quebec Superior CourtCase Number
500-17-129420-249Practice Area
Civil litigationAmount
Not specified/UnspecifiedWinner
DefendantTrial Start Date